5 new MAGU passive houses near Vienna – shell construction completed in 7 weeks

From the groundbreaking to the completion of the shell in just seven weeks—with the MAGU building system, fast, precise, and energy-efficient construction is a reality. This construction project involved the creation of five passive houses near Vienna. Thanks to the excellent collaboration with our loyal client, Abfalter Bau GmbH, this project was completed on schedule and to the highest standards of workmanship.
Click on the image to enlarge it

Project Timeline at a Glance

22.11.2016

First shipment of MAGU Atlas floor slab forms for Houses 1, 3, and 5.

02.12.2016 & 08.12.2016

Delivery of MAGU wall elements, roller shutter boxes, as well as the intermediate floors and the flat roof.

12.01.2017

Photo documentation of the construction site—just seven weeks after the foundation slab was delivered.
Delivery of MAGU wall and ceiling elements to the construction site
Passive houses at the structural completion stage, seven weeks after the project began
The result: Five modern, airtight passive houses built in no time.

MAGU Components Used

  • MAGU Floor Panel Trough
  • MAGU WS Wall Panels
  • MAGU Roller Shutter Box
  • MAGU Intermediate Roofs (available in either flat or pitched roof styles)
All components are manufactured in-house and were prefabricated using energy-efficient methods.